West Wyalong Solar Farm Project

Project Details

Client:

Lightsource bp Australia

Location:

West Wyalong, NSW

Project Date :

2021

Website :

The Problem

The West Wyalong Solar Farm Project required a precise and timely delivery of stock, necessitating arrivals at the site from 7 am, a challenging feat given the 6-7 hour travel time from Sydney. This tight schedule demanded an innovative logistical approach to meet the project’s specific needs without compromise.

The Solution

Understanding the criticality of the project’s timeline, we initiated an overnight loading operation. By starting to load trucks from midnight, we ensured that each delivery could reach the solar farm site right from the opening hour of 7 am. This meticulous planning and execution underscored our commitment to meeting client expectations through adaptable and efficient logistics solutions.
  • 7 hours: Shipping distance from warehouse
  • 20 tonnes per container
  • 200 loads transferred on B-double trucks

Project Summary

Our tailored solution facilitated the seamless reception of each load at the solar farm within the designated slot times, thereby maintaining the project’s momentum. The operation’s success was marked by the delivery of over 300 containers and more than 200 loads of B-double trucks over three months. This case study exemplifies our dedication to delivering reliable and punctual service, reinforcing our position as a leader in complex logistical challenges.